Solar Compute Campus: Georgia design

This is the earlier design, kept for reference. The campus is now planned for Norway and powered by its own hydro, wind and solar plus the grid: see the Nordic Compute Campus.

Status: Superseded by the Norway design.

A 1.5 MW AI compute facility designed for a rural north Georgia site, running on sunlight around the clock. A 20 MWdc array and 60 MWh of lithium iron phosphate storage carry the load day and night for roughly 96.5% of the year, with a grid connection covering the residual winter cloudy stretches and two Tier 4 Final diesel sets held in reserve for utility outages.

The design rests on one idea: a compute load is among the very few industrial loads that can be throttled to a fraction of nameplate in seconds without damage. That makes it an unusually good partner for intermittent generation — and it means surplus midday output, rather than being wasted, can be spent on interruptible work.

Design Basis

The facility is sized at 1.5 MW of IT critical load, drawing roughly 1.83 MW at the meter and consuming about 16,000 MWh per year at a near-100% load factor. Climate figures are taken for 34.0°N — the Athens and Madison County area — where a well-oriented fixed-tilt array yields in the region of 1,450 kWh per kWdc per year.

Two rules drive most of the engineering. The first is to stay below every cost and regulatory cliff: under 30 kW per rack so the halls remain air-cooled, effectively zero export so no generator interconnection study is triggered, and far below the 100 MW threshold at which Georgia Power's large-load contract regime applies. The second is to separate durable assets from disposable ones — the building, electrical service and solar array are built once for the full capacity, while compute hardware is purchased in tranches against contracted demand.

Compute Platform

Conventional 4U eight-GPU servers rather than the dense NVL72-class racks used in hyperscale AI halls. Dense racks would fit the same load into about eleven cabinets, but at roughly three times the hardware cost per megawatt, with mandatory direct-to-chip liquid cooling and floors rated for concentrated loads above 400 lb/ft². The conventional route uses commodity parts a small local team can service.

The most consequential single decision is the GPU power cap. Each card is configured at 450 W rather than its 600 W maximum. Because the real constraint on this site is megawatts rather than GPU count, capping each card fits 27% more silicon behind the same electrical service, the same cooling plant and the same solar array, at a single-digit percentage cost in per-card throughput.

Rack density options, and where air cooling stops working
Servers/rack kW/rack Racks Cooling required
419.172Conventional air with containment; wasteful of floor space
523.958Air with strict containment
628.748Selected. Containment plus rear-door heat exchangers, just below the ~30 kW economic inflection
733.542Rear-door heat exchangers mandatory, direct-to-chip advisable
838.336Direct-to-chip liquid cooling territory

At full build this is 48 compute racks plus eight network and storage racks, arranged in two independently contained halls so either can be serviced without disturbing the other. A populated rack weighs around 620 lb, so an ordinary concrete slab with overhead containment is sufficient — no raised floor and no structural upgrade.

Thermal Design

Rear-door heat exchangers on every rack, fed by a chilled-water loop and rejecting heat through closed-loop dry coolers, with adiabatic pre-cooling available for the handful of Georgia summer afternoons that need it. Capturing heat at the rack keeps the hall itself near ambient, so a cooling fault degrades gradually rather than catastrophically.

The loop is closed, which means the facility consumes no water in normal operation. The adiabatic pre-cooling uses a small amount of water on the hottest afternoons only. For scale, applying a published fleet-average water usage effectiveness of 0.27 litres per kWh to this load would imply roughly 3.5 million litres a year. Dry cooling avoids essentially all of it, at some efficiency cost in August. In a state where data centre water draw is becoming a live political issue, this is a deliberate design choice rather than an incidental benefit.

Cooling redundancy is N+1 on every component, with an automatic load shed that drops the burst tier on rising temperature, falling chilled-water flow or falling differential pressure — rather than waiting for the GPUs to throttle themselves. At this power density a total cooling failure drives the space through thermal limits in single-digit minutes, which is faster than any human response.

Energy Strategy

Running a constant 1.83 MW load on sunlight through the night is not solved by picking an array size. The binding constraint is not annual output but the worst consecutive run of overcast December days, so the sizing has to be simulated rather than calculated. December generation here averages 2.70 kWh per kWdc per day; covering a December day — ten hours of direct supply plus fourteen hours from storage — needs about 17 MWdc. Sizing for a heavily overcast December day instead would need 62 MWdc across 340 acres, which nobody builds.

The design therefore trades array size against battery size. A daily simulation across twelve months, with a realistic mix of clear, partly cloudy and overcast days, puts the practical knee at 20 MWdc with 60 MWh of storage: 96.5% of all hours served by sunlight, on about 110 acres, leaving roughly 563 MWh of annual grid import — some thirteen days' worth, scattered across winter.

Simulated share of annual load served by solar and storage alone
Solar MWdcBattery MWh Load servedGrid import MWh/yrAcres
4832.8%10,78222
144086.6%2,15777
166093.5%1,03988
206096.5%563110
2410099.6%72132
2812099.9%18154

The table also shows why "always" is a target rather than a state. Going from 16 to 20 MWdc buys 3.0 points of coverage; the next step buys 3.1 points for more money; the step after that buys 0.3 points. True 100% is never reached at any price, because there is always a worse cloudy week than the one the array was sized for. Something cheap has to cover the tail, and a grid connection that sits idle 96% of the year is by far the cheapest option available.

Surplus and Interruptible Compute

A 20 MW array behind a 1.83 MW load produces far more at midday than the load and the battery can absorb. The simulation shows about 9,700 MWh a year curtailed — more than 60% of the firm load's entire annual consumption.

That surplus is not really waste; it is the cheapest energy on the site, available in a predictable daily window. At roughly 4.8 kW per server it represents about two million node-hours a year, enough to run several hundred additional servers on a daylight duty cycle at a marginal energy cost near zero. The intended commercial shape follows from this: firm, battery-backed capacity sold at a premium, and interruptible solar-hours capacity sold cheap to batch training and render work that does not care when it runs.

Storage and Resilience

Sixty megawatt-hours of lithium iron phosphate storage does four jobs at once: it carries the load every night, it absorbs the midday surplus, it replaces a conventional static UPS for ride-through, and it supports the curtailment ladder below. One caveat matters and is stated plainly: this pack cycles every night by design. It is not a reserve sitting at full charge waiting for a fault, so on a December evening it may already be well down when the utility fails. The durations below are best-case, and the control policy reserves a floor that is never used for load-shifting.

What the battery actually buys, by operating tier
Operating tier IT load On battery Role
Full build, all racks1.50 MW25.1 hNormal operation; also the nightly cycle depth
Base tier, 32 racks0.92 MW41.0 hFirst automatic curtailment step
Core tier, 12 racks0.34 MW109 hContracted-SLA workloads only
Control tier, 2 racks0.06 MW459 hNetwork, storage and monitoring; daytime solar sustains this tier indefinitely regardless of season

Emergency Generation

Two 1,250 kW diesel sets in parallel, with 12,000 gallons of fuel in two double-wall tanks, cover utility outages that outlast the battery. Either set alone carries the base tier, so a single engine failing to start — the classic data centre outage — does not take the facility down. Together they run at about 73% load, comfortably inside the efficiency band and clear of the low-load fouling that troubles lightly loaded standby diesels.

Having built the storage first changes what kind of generator plant is needed. The power conversion system has already picked up the entire load at the instant the utility fails, so the sets inherit no ten-second start requirement and no block-load step; they ramp onto a load the battery is already carrying. The controller starts an engine on state of charge rather than on outage detection — below roughly 60%, or when an outage is forecast to outlast the pack. Every momentary interruption and recloser operation is absorbed silently and never cranks an engine at all.

The sets are specified to EPA Tier 4 Final rather than the lower tier an emergency engine may lawfully use. Even running a full statutory allowance of non-emergency hours, the generators would add under 4% to the facility's operational carbon, so carbon is not the argument against them — local nitrogen oxide and particulate emissions are, and those are precisely what aftertreatment addresses. Several states have already moved toward Tier 4-equivalent baselines for new data centre diesels, so the cleaner specification also protects against a rule change inside the plant's service life.

One boundary is deliberate and worth stating: the generators cover utility outages only, never cloudy weather. Running an emergency engine because the sun is behind cloud is ordinary non-emergency operation under federal rules, capped at 100 hours a year, and exceeding that cap would permanently reclassify the engines. The grid covers the weather; the generators cover faults.

Combined duration by condition
ConditionDurationMechanism
Momentary interruptionUnlimitedPower conversion system; no transfer, no engine start
Outage up to a day, full load25 hBattery alone
Extended outage, full load~99 hBattery, then both generators on stored fuel
Extended outage, base tier~161 hOne generator, burst tier shed
With fuel resupplyIndefiniteStanding fuel contract with priority delivery
Core tier, no fuelIndefiniteThe array sustains the core tier on solar alone through any December week

That supports continuous operation through any realistic Georgia weather event. It is still not a Tier III facility — there is no concurrent maintainability on the electrical path and no second utility feed — and customers are quoted the real figures rather than aspirational ones. Workloads that checkpoint and can pause are the intended fit.

Build Sequence

The campus is designed to be built in five stages, each with a defined gate that must be passed before the next is funded. No stage is committed on a demand forecast.

  1. Site control. Land, zoning, utility load application, transformer order, fibre contracts and engineering design. Transformers are ordered first, because current lead times run from roughly nine months to over two years and nothing else proceeds without them.
  2. Pilot hall. Building shell and electrical service for the full capacity, mechanical and electrical fit-out for a third of it, the first 2 MW solar block with 6 MWh of storage, and the first 150 kW of compute.
  3. Proving stage. Fit-out completed to 500 kW with a 6.7 MW array and 20 MWh, and measured efficiency verified across a full Georgia summer before any further expansion.
  4. Scale. Fit-out to 1.0 MW, array to 13.3 MW and 40 MWh, the second service transformer energised, and the first generator set installed.
  5. Full build. Fit-out to 1.5 MW, array to 20 MW and 60 MWh, and the second generator set.

The array scales with the load rather than being built out in front of it, because round-the-clock solar is a ratio — roughly 11 MWdc and 33 MWh per megawatt of facility load. Phase one's 2 MW array covers its 183 kW facility as completely as 20 MW covers the full build, so every phase is fully solar-powered on its own terms. The building shell and electrical service are the exception: those are built once for the full capacity, since retrofitting either costs several times what oversizing does, and transformer lead times make a later decision a two-year delay.

Status

In the beginning of development: this is the design stage. No site has been selected. The campus now needs roughly 140 acres — about 110 of them for the array — which in the Georgia piedmont means assembling several parcels, so land is being approached through options rather than purchases.

Site selection is gated on four things that must be confirmed in writing before any land is committed: distribution capacity within reach of a 1.83 MW load; an interconnection position for a 20 MW generating facility, which is the harder of the two electrical questions even in a non-export configuration; two genuinely diverse fibre routes to the parcel; and the county's exact 2020 census population, which determines the applicable threshold under Georgia's high-technology data centre equipment exemption.

In the beginning of development. Specifications may change. Performance figures on this page are calculated from published equipment specifications and regional climate data, not from measured site results. The 96.5% solar coverage figure comes from a daily simulation using modelled monthly irradiance and a synthetic distribution of clear and cloudy days — not from site measurements or a typical meteorological year file. Cooling efficiency, solar yield, battery cycle life and equipment pricing are each subject to verification before construction.